What production environment allows a good or service to be made after receipt of a customer's order?

Enhance your understanding of Master Planning with our targeted exam prep materials. Use flashcards, multiple choice questions, and explanations to study effectively. Prepare confidently for the APICS MPR Exam!

The production environment that enables a good or service to be produced only after a customer's order has been received is known as Make to Order. This approach is particularly beneficial for customized or specialized products, where the product specifications can vary significantly based on individual customer requirements.

In a Make to Order setting, the manufacturing process starts only after confirmation of a customer's order, which allows for greater flexibility in accommodating changes in customer preferences or specifications. It helps in minimizing unnecessary inventory costs and reduces the risk of overproduction, as production is directly linked to actual demand.

In contrast, the other environments such as Make to Stock involve producing goods based on forecasted demand and stocking them for future orders, leading to potential excess inventory. Assemble to Order does allow for some customization but typically involves pre-manufactured components assembled after an order is placed, rather than a complete manufacturing process starting from scratch. Engineer to Order is similar in that products are designed and built to customer specifications but often involves a longer lead time due to the extensive engineering and design processes required before manufacturing can commence.

Thus, Make to Order stands out as the environment defined by production occurring strictly after receipt of an order, ensuring products are tailored to meet specific customer needs while managing inventory efficiently.